This free production schedule template is an Excel file that turns a list of orders into end dates, a late-order check, load by week against capacity for each work center, and a four-week bar chart. It uses ordinary formulas and conditional formatting, with no macros, so you can see and change how every number is worked out.
Free download. Download the production schedule template (.xlsx). Five sheets, sample data for a small machine shop, no macros.
Below: what is in the file, how to use it step by step, how to set capacity and sequence orders, what the sample shows, and where a spreadsheet schedule stops being enough.
What is in the production schedule template
- How to use: the steps below, what the colors mean, and the template’s limits.
- Work centers: machines, hours per shift, shifts per day and efficiency for each work center, with capacity per day and per week worked out. Also the plan start date and your plant holidays.
- Orders: one row per operation, with order number, product, quantity, due date, priority (1 to 5, checked on entry), work center (picked from a list), setup hours and run hours per unit. It works out total hours, working days, end date, whether the operation ends late and by how many days, and the ISO week it starts in.
- Load by week: hours booked on each work center for eight weeks against its capacity, red over 100% and amber from 90%.
- Schedule: a day-by-day grid for four weeks. Blue bars for planned operations, red bars for operations that end after their due date, D on the due date, grey for weekends and holidays.
Header rows are frozen, inputs are white and formulas are grey, so it is clear where to type.
How to use it, step by step
- Clear the sample data. Rows marked SAMPLE are an example machine shop. Select the white cells and press Delete. Do not delete whole rows: the other sheets read the rows one by one.
- Enter your work centers. For each machine group or line, enter how many machines or stations it has, hours per shift, shifts per day and efficiency. Use the names people use on the floor.
- Set the plan start and holidays. Enter the Monday your plan starts and list your plant holidays. Every date skips weekends and holidays.
- Enter one row per operation. An order that goes saw, mill, then assembly takes three rows with the same order number, quantity and due date. Take setup hours and run hours per unit from your routing or from recent jobs.
- Sequence and set start dates. Sort the rows into the order you want to run them (Data, Sort), then give each operation a start date after the previous operation of the same order ends and after the job before it on that work center.
- Read the results. Total hours = setup + run per unit × quantity. Working days = total hours ÷ the standard hours one machine delivers a day, rounded up. End date = that many working days from the start. Late? compares the end date with the due date.
- Check load by week. Fix every red cell before the week starts: move start dates, add overtime, or move work to another work center.
- Update it daily. Clear what finished, move what slipped and add new orders.
Example inputs, not real data. From the sample file: order 1001 on the CNC mill is 60 pump housings at 3.0 setup hours and 0.60 run hours each, so 3.0 + 0.60 × 60 = 39.0 hours. One mill delivers 8 hours × 2 shifts × 85% = 13.6 standard hours a day, so the job needs 39.0 ÷ 13.6 = 2.9, rounded up to 3 working days. It starts Tuesday, December 1 and ends Thursday, December 3, before its December 11 due date.
How to set capacity
Capacity per day = machines × shifts × hours per shift × efficiency
The weekly figure on Load by week multiplies that by the working days in each week, so a holiday week has less. Efficiency is the number to get right. It is the share of staffed hours that turn into standard hours of good work, so it covers breakdowns, waiting for material or an operator, and running slower than the routing says. Work it out from last month: standard hours of the work you finished ÷ hours the machines were staffed. Leave it at 100% and every plan will come up short.
Capacity planning in manufacturing explains the parts of this number, and the machine capacity calculator works it out for one work center. To plan a few weeks of overtime, raise hours per shift for that work center while it lasts, then set it back.
How to sequence the orders
The template does not choose the order for you. Sort the Orders rows by the rule you use, then set start dates down the list:
- Priority, then due date: what most planners do by hand.
- Earliest due date: the order due first runs first.
- Critical ratio: time left until the due date ÷ work left; the lowest ratio runs first.
- Shortest processing time: gets the most orders through, but long jobs wait.
Production scheduling rules compares them with worked examples. Whatever the rule, schedule your bottleneck work center first and set the others around it.
What the sample file shows
The sample data has the three problems the template is built to catch.
- An overloaded week. The CNC mill has 153.5 hours booked in ISO week 50 against 136.0 hours of capacity, 113%, because the start dates put four jobs on two mills on December 9 and 10. Moving orders 1006 and 1012 to Monday, December 14 brings week 50 down to 95.0 hours (70%) and puts week 51 at 58.5 hours (43%), and both still end before their December 18 due date.
- A late order. Manifold 1005 needs 3 working days from December 7 and is due December 8, so it shows Late by 1 day. Starting it Friday, December 4 makes it end on its due date. The mill’s week 49 then reads 135.5 hours, 99.6% and amber: full, but possible.
- A holiday. December 24 and 25 leave assembly 3 working days and 45.6 hours in week 52. Valve assembly 1013 needs 6 working days, so it ends December 30, 7 days late. Starting it Wednesday, December 16 gets it done on December 23. It then runs past a Friday, so split the row in two, one per week.
That last point is the template’s main simplification: hours count in the week an operation starts. The column Runs past Friday? flags every operation you should split so its hours land in the right weeks.
Where a spreadsheet schedule breaks down
A template like this works while one planner owns the schedule and the open orders fit on a screen. Past that, the limits show:
- One person. The file lives on one laptop. Two people editing copies get two schedules, and nobody knows which is current.
- No finite loading. Excel lets you book four jobs on two machines on the same day. Load by week tells you afterwards; it does not move anything. A finite-capacity scheduler never books a machine past its hours and gives you the real finish date instead.
- No materials check. The file does not know whether the steel or the components are in. A job that is scheduled but short of material will not run.
- Manual updates. Every finished job, breakdown and rush order is typed in by hand, so the plan is only as current as the last update.
Signs your plant has outgrown spreadsheet inventory management covers the same tipping point for stock. When the schedule reaches it, production scheduling software does the finite loading and the materials check, and takes progress reports from the floor. The Lab’s Production Planning add-on imports work centers, routings and production orders from Excel or CSV files, schedules them to finite capacity on a Gantt chart you can drag, and checks materials order by order, from $99 a month.
Common mistakes
- Leaving efficiency at 100%, so every week looks possible and every week ends late.
- One row per order instead of one per operation, so all the hours land on one work center.
- Start dates that ignore the operation before: the mill cannot start before the saw has cut the bar.
- Fixing red weeks by raising capacity on paper instead of changing the plan.
- Updating once a week. By Wednesday the file no longer matches the floor.
Ready to plan your own week?
Download the free template, or see the Lab’s Production Planning add-on schedule the same kind of orders to finite capacity, with no sign-up for the demo.
Frequently asked questions
Does the template use macros?
No. Everything is ordinary formulas, data validation and conditional formatting, so you can see how each number is worked out and change it.
Which version of Excel do I need?
It was built for Excel for Microsoft 365 and recent desktop versions. The newest function it uses is ISOWEEKNUM, which Microsoft lists for Excel 2016 and later, Excel for Microsoft 365 and Excel for the web.
Why does an operation say “Yes: split”?
Hours count in the week an operation starts. When an operation runs past a Friday, split it into two rows, one per week, with the quantity divided, so Load by week puts the hours in the right weeks.
Can the template schedule to finite capacity?
No. It shows when a work center is overbooked, but you move the dates. Finite-capacity scheduling software puts each operation on a machine only when that machine is free.
Sources: ISOWEEKNUM function, Microsoft Support (Excel versions listed).