Supply planning is the work of turning your demand plan into purchase, production and transfer plans you can carry out within the limits of your capacity, your stock and your suppliers. For every item it answers three questions: how much to bring in, from where, and when.
Demand planning decides how much you expect to sell. Supply planning decides how you will meet that number, and what to do where you can’t. Run together each month, the two are what most people mean by demand and supply planning. This guide covers the steps, a worked example for one item, the outputs and KPIs, and where software helps.
Supply planning vs demand planning
In a small company the same person often does both, so the two blur together. They answer different questions and fail in different ways.
| Demand planning | Supply planning | |
|---|---|---|
| Question | How much will we sell? | How do we supply it, and can we? |
| Main inputs | Sales history, market input, customer forecasts | The demand plan, stock, open orders, lead times, capacity, supplier limits |
| Output | One agreed forecast by family and item | Planned purchase, production and transfer orders, and projected stock |
| Limits it respects | None: it states what customers want | Capacity, supplier minimums and limits, cash, space |
| Typical owner | Sales with the planner | The planner or buyer, with production |
Keep the demand plan honest. If the forecast is cut to fit what you think you can make, the shortage disappears before anyone decides what to do about it. Let the demand plan say what customers want and let supply planning show the gap. Our six-step demand planning process covers the demand side.
The supply planning process in seven steps
- Net the requirements. For each item and period, take the demand plan, add the buffer you plan to keep (step 2), and subtract stock on hand and open purchase and production orders. What is left is the net requirement.
- Set inventory targets and safety stock. Decide how much buffer each item carries, based on how much its demand and lead time vary and what a shortage costs. Our guide compares three safety stock formulas.
- Choose the source and apply its rules. Decide whether each requirement is bought, made or moved from another location. Apply that source’s lead time, minimum order and order multiple, and move each order back by its lead time so you know when to place it.
- Check capacity. Add up the hours the planned production orders need on each work center by week and compare them with the hours you have. For bought items, check what each supplier can ship in a month. Cash and warehouse space are limits too.
- Build the constrained plan. Where the plan breaks a limit, change it: build or buy earlier, split an order between suppliers, add overtime or a shift, move stock from another location, or agree a later date with the customer. For the items you make, the result becomes your master production schedule (MPS).
- Work the exceptions. Review only what needs a decision: items projected below safety stock, late or unconfirmed purchase orders, orders to pull in or push out, and stock building up with no demand behind it.
- Sign off in S&OP. Bring the gaps you could not close to the monthly meeting, with the cost of each option, and leave with decisions and owners. Making those decisions matters more than the label, and how S&OP, SIOP and S&OE differ is mostly a question of scope and rhythm.
Most small companies run the full cycle monthly, with a short weekly check of exceptions between meetings.
The netting formula
Net requirement = forecast + safety stock − (projected on hand + scheduled receipts)
If the result is zero or below, nothing is needed that period. If it is above zero, round it up to the order multiple or minimum to get the planned receipt, then move it back by the lead time to get the planned order release. This is the same arithmetic that material requirements planning (MRP) uses for components. Supply planning applies it to the items you sell, and MRP carries it down the bill of materials.
A worked example: one item, six months
Example inputs, not real data. A valve you buy finished and sell from stock. At the start of month 1 you have 400 on hand and a purchase order for 200 due in month 1. Safety stock is 100, the lead time is one month, you order in multiples of 50, and the supplier can ship at most 300 a month.
| Month | 1 | 2 | 3 | 4 | 5 | 6 |
|---|---|---|---|---|---|---|
| Forecast | 250 | 300 | 150 | 420 | 300 | 280 |
| Open purchase order | 200 | 0 | 0 | 0 | 0 | 0 |
| Net requirement | 0 | 50 | 150 | 420 | 270 | 250 |
| Planned receipt | 0 | 50 | 150 | 450 | 300 | 250 |
| Projected on hand | 350 | 100 | 100 | 130 | 130 | 100 |
| Planned order release | 50 | 150 | 450 | 300 | 250 | – |
Month 1 needs nothing: 400 on hand plus 200 arriving, less 250 sold, leaves 350. In month 2, 350 less a forecast of 300 leaves 50, which is below safety stock, so the net requirement is 300 + 100 − 350 = 50. Month 4 is the seasonal peak: 420 + 100 − 100 = 420, rounded up to 450. Each planned receipt is released one month earlier, so the month 4 receipt is an order placed in month 3. The release in month 6 depends on the forecast for month 7.
Now apply the supplier limit
The plan asks for 450 in month 4, but the supplier can ship only 300. Month 3 has room, because its receipt is only 150, so 150 of the month 4 quantity moves there.
| Constrained plan | 1 | 2 | 3 | 4 | 5 | 6 |
|---|---|---|---|---|---|---|
| Planned receipt | 0 | 50 | 300 | 300 | 300 | 250 |
| Projected on hand | 350 | 100 | 250 | 130 | 130 | 100 |
| Planned order release | 50 | 300 | 300 | 300 | 250 | – |
The constrained plan never drops below safety stock, and the six months still end at 100 units: 600 at the start plus 1,200 received, less 1,700 sold. The price is 150 extra units carried through month 3. The alternatives are a second source, an expedite fee or a shortage in the peak month. Each has a cost, and comparing them is what the S&OP meeting is for.
What supply planning produces
- Planned purchase orders by supplier, with order dates and quantities.
- Planned production orders, which feed the production plan and the shop schedule.
- Transfer orders that move spare stock between locations before you buy more.
- Reschedule messages: open orders to pull in, push out or cancel.
- Projected inventory by item and month, in units and dollars.
- A capacity summary: load against available hours by work center and week.
- A short list of gaps for the S&OP meeting, each with its options and costs.
Supply planning KPIs
| KPI | Formula | What it tells you |
|---|---|---|
| Fill rate | Units shipped ÷ units ordered | Whether the plan protected customers |
| Inventory turns | Cost of goods sold ÷ average inventory value | Whether it did so without carrying too much stock |
| Forecast-to-plan adherence | Units covered by the supply plan ÷ units in the demand plan, by family and month | Whether you planned to meet demand at all |
| Plan attainment | Units received or made in the planned period ÷ units planned for that period | Whether the plan was carried out |
| Supplier on-time | Lines received on or before the promised date ÷ lines received | Whether supplier dates and lead times can be trusted |
Read fill rate and turns together, because either one is easy to improve by hurting the other. If forecast-to-plan adherence sits below 100% month after month, you are planning shortages before the month starts. Forecast accuracy itself is a demand planning measure, so report it there.
Spreadsheets or software?
A spreadsheet handles supply planning for a few dozen items at one location: one row per item, a column per month and the netting formula copied across. It breaks down when stock and open orders change daily but the file is rebuilt weekly, when lead times and order multiples differ by supplier, or when two locations can lend each other stock.
That is the job of demand and supply planning software. It nets every item at every location each time the data changes, applies order rules and lead times, and lists only the exceptions. Before you buy, check that a tool shows you where a plan breaks a limit, not only a list of shortages, and that it explains each suggested order. Our guide to choosing inventory planning software lists what else to test on your own data.
The Statadventure Lab works from your Excel or CSV files, with database connections on the Planner and Growth plans. On those plans, its replenishment planner works out safety stock, reorder points, suggested orders and transfers for every item at every location, and moves spare stock before buying more. Supplier confirmations let the plan use the dates suppliers confirm instead of the original due dates. For the items you make, the Production Planning add-on, at $99 a month, shows the load on each work center by week and whether each production order’s materials are ready, waiting or short.
Common mistakes
- Cutting the forecast to fit capacity, so the shortage never reaches a decision.
- Counting stock you cannot use: quarantined, rejected or already promised to another order.
- Planning from quoted lead times instead of the ones suppliers actually deliver.
- Treating a late purchase order as if it will arrive tomorrow.
- Setting safety stock once and never revisiting it.
- Ignoring order minimums and supplier limits until the purchase order is placed.
- Changing the plan outside the meeting, so production and purchasing work from different numbers.
Want to see a supply plan built from your own files?
The live demo runs the Statadventure Lab on a sample company, with no account needed.
Frequently asked questions
What is supply planning?
Supply planning turns the demand plan into purchase, production and transfer plans that fit your capacity, stock and supplier limits. It decides how much of each item to bring in, from where and when.
What is the difference between demand planning and supply planning?
Demand planning estimates how much you will sell. Supply planning decides how to meet that demand with purchasing, production and inventory, and shows where you cannot.
How often should you run supply planning?
Monthly for the full plan, timed to feed the S&OP meeting, with a weekly check of exceptions such as late purchase orders and items falling below safety stock.
Can you do supply planning in Excel?
Yes, for a few dozen items at one location. It gets hard when stock and open orders change daily, order rules differ by supplier, or several locations share stock.