Free machine capacity and utilization calculator
Work out the hours a group of machines can really deliver in a week, set this week’s work against it, and see the capacity utilization and how many hours you are over or under. Enter the load as total hours, or as units and run times with setups. It runs in your browser. Nothing you enter is stored or sent.
- Gross machine hours
- Scheduled hours after planned maintenance
- Available capacity
- Load
- Utilization
- Hours over capacity
Estimates for planning only. This is a weekly total for machines that can share the work. It does not check due dates, the order of operations or whether the right people are on shift. Results depend entirely on the numbers you enter and are not professional advice.
How machine capacity is calculated
Capacity starts with the hours the machines are staffed, less planned maintenance, and is then reduced by efficiency to the hours they really produce. Load is the work due in the same week at standard times. Utilization compares the two.
Gross machine hours = machines × shifts per day × hours per shift × working days per week
Available capacity = (gross machine hours − planned maintenance) × efficiency
Load = hours of work, or (units × run time per unit + setups × setup time) ÷ 60
Utilization = load ÷ available capacity × 100
Hours over capacity (or to spare) = load − available capacity
Extra shifts needed = hours over ÷ (hours per shift × efficiency), rounded up
Over 100% means the week’s work does not fit. Run the calculator for the machine group you think is the bottleneck first. The guide to capacity planning in manufacturing shows how to do this week by week and what to change when load runs over.
A worked example
Example inputs, not real data
A work center has 3 machines running two 8-hour shifts, 5 days a week, with 6 hours of planned maintenance across the three machines this week. Efficiency is left at the 85% assumption. This week’s orders need 1,300 units at 9 minutes each, plus 12 setups at 45 minutes each.
- Gross machine hours = 3 × 2 × 8 × 5 = 240 hours
- Available capacity = (240 − 6) × 85% = 234 × 0.85 = 198.9 hours
- Load = (1,300 × 9 + 12 × 45) ÷ 60 = (11,700 + 540) ÷ 60 = 204 hours
- Utilization = 204 ÷ 198.9 = 102.6%
- Over capacity by 204 − 198.9 = 5.1 hours
One extra 8-hour shift on one machine adds 8 × 0.85 = 6.8 hours, enough to cover the 5.1. Taking 10 minutes off each of the 12 setups would free another 2 hours. Use the Load example button above to run these figures, and see setup time reduction (SMED) for ways to shorten changeovers.
Frequently asked questions
What efficiency should I use?
Use your own figure if you track one: hours of work produced at standard times divided by the hours the machines were scheduled. The 85% filled in is only a starting assumption. If you track OEE and your run times are ideal times, OEE is a reasonable figure to use.
Is capacity utilization the same as OEE?
No. Utilization compares the work you have with the hours you can supply. OEE measures how well a machine runs during the time it is scheduled. A machine can be fully loaded and still have a low OEE.
What can I do if load is over capacity?
Add hours with overtime or an extra shift, move work to another machine or another week, cut setup time, or send some work to an outside supplier. Check the bottleneck first: extra hours anywhere else do not raise output.