Free takt time calculator
Work out takt time, the pace customer demand sets, from your shifts, breaks, working days and demand. Add your slowest step and the total work content to see whether the line keeps up and how many stations or operators it needs. It runs in your browser. Nothing you enter is stored or sent.
- Available time per day
- Available time in the period
- Takt time
- Takt time in minutes
- Units per hour needed
- Units per day needed
- Slowest step as a share of takt
- Does the slowest step keep up?
- Work content ÷ takt time
- Minimum stations or operators
Estimates for planning only. The station count is a theoretical minimum: it assumes the work splits evenly across stations with no waiting. Results depend entirely on the numbers you enter and are not professional advice.
How takt time is calculated
Takt time is the time available to make one unit if you are to meet demand exactly. It comes from the clock and the customer, not from your machines. Compare it with the cycle time at each step: any step slower than takt cannot keep up.
Available time = (shift length − breaks per shift) × shifts per day × working days
Takt time = available time ÷ customer demand
Units per hour needed = customer demand ÷ available hours
Slowest step share of takt = cycle time at the slowest step ÷ takt time × 100
Minimum stations or operators = total work content ÷ takt time, rounded up
A step at or under 100% of takt keeps up. Above 100%, it falls behind by the difference on every unit. The guide to takt time vs cycle time vs lead time explains how the three measures fit together.
A worked example
Example inputs, not real data
A plant runs two 480-minute shifts a day, with 30 minutes of breaks in each, 5 days a week. Customers need 3,000 units this week. The slowest step takes 82 seconds a unit, and all the steps together take 410 seconds a unit.
- Available time = (480 − 30) × 2 × 5 = 4,500 minutes, or 270,000 seconds (75 hours)
- Takt time = 270,000 ÷ 3,000 = 90.0 seconds a unit, or 1.50 minutes
- Units per hour needed = 3,000 ÷ 75 = 40.0
- Slowest step = 82 ÷ 90 = 91.1% of takt, so it keeps up with 8 seconds a unit to spare
- Minimum stations or operators = 410 ÷ 90 = 4.56, rounded up to 5
Those 8 seconds a unit add up to 24,000 seconds, or 400 minutes, of slack at the slowest step over the week (8 × 3,000). More downtime than that at that step and the week’s demand is late. Use the Load example button above to run these figures, and the machine capacity calculator to check the hours on each machine.
Frequently asked questions
What is the difference between takt time and cycle time?
Takt time is the pace customer demand sets: available time divided by the units needed. Cycle time is how long a step actually takes to finish one unit. If a step’s cycle time is longer than takt time, that step cannot keep up without more time or more capacity.
What should I take out of available time?
Take out time the line is planned to stop, such as breaks, lunches, meetings and planned maintenance. Leave breakdowns, changeovers and slow running in: those are losses your cycle times have to absorb, not time you planned away.
What can I do if the slowest step is slower than takt?
Add time at that step with overtime or another shift, add capacity there with a second machine or operator, or cut its cycle time by moving work to other steps or reducing setups. Fix the slowest step first, because extra time anywhere else does not raise output.
Related tools and reading
Schedule against this capacity every day
Production Planning, $99 a month. It puts every operation on a machine of its work center, never overlapping another job or planned maintenance, and gives you a dispatch list.
See Production Planning