Should you make a part in-house or buy it from a supplier? The question comes up when a machine needs replacing, a supplier raises prices, capacity gets tight or a quote arrives that looks cheaper than your own cost. The answer depends on which costs you count. This framework walks through the steps, shows a worked example and lists the mistakes that most often tip the decision the wrong way. The make vs buy calculator runs the cost side for you.
The formulas
Annual make cost = variable cost per unit × annual volume + avoidable fixed cost
Landed buy cost per unit = supplier price + freight + duty + other per-unit costs
Break-even volume = avoidable fixed cost ÷ (landed buy cost per unit − variable make cost per unit)
Variable make cost covers material, direct labor and the overhead that rises and falls with volume, such as power and consumables. Avoidable fixed cost is the fixed spending that would end if you stopped making the part: a leased fixture, a dedicated setup technician, a maintenance contract on a single-purpose machine. Fixed costs that continue either way are not part of the decision.
The framework, step by step
- Define the part and the volume. Use the volume you expect over the next two to three years, not last year’s.
- Build the make cost from the bottom up. Take material and labor from the routing and bill of materials, then add variable overhead.
- Find the avoidable fixed cost. Ask what would actually stop if the part moved out. Be strict.
- Build the landed buy cost. Start from the quote, then add freight, duty, incoming inspection and the cost of carrying the larger lots or longer lead time the supplier may require. The landed cost calculator helps with freight and duty.
- Compare at the planned volume and find the break-even.
- Score the factors besides cost before deciding (see below).
Worked example (hypothetical numbers)
Example inputs, not real data. A plant machines 8,000 brackets a year. Material is $6.10, direct labor $3.40 and variable overhead $1.25 a unit. The cost system also allocates $4.00 a unit of general factory overhead, which would stay if the part were bought. A dedicated fixture lease and part of a setup technician’s time, $14,000 a year, would end. A supplier quotes $11.90 a unit; freight is $0.45 a unit and incoming inspection plus carrying the supplier’s larger lots adds $0.35 a unit.
- Variable make cost = 6.10 + 3.40 + 1.25 = $10.75 a unit
- Annual make cost = 10.75 × 8,000 + 14,000 = $100,000, or $12.50 a unit
- Landed buy cost = 11.90 + 0.45 + 0.35 = $12.70 a unit
- Annual buy cost = 12.70 × 8,000 = $101,600
- Making is cheaper by $1,600 a year at this volume
- Break-even = 14,000 ÷ (12.70 − 10.75) = about 7,180 units a year
Now look at what happens with the full standard cost. Adding the $4.00 allocated overhead makes the in-house part look like $16.50 a unit, and the $11.90 quote looks like a $36,800 annual saving. But that $32,000 of overhead does not leave with the part; it is spread over the remaining work. In this example, buying would raise total cost, not cut it. Above 7,180 units a year, making stays cheaper; below it, buying wins on cost.
Factors besides cost
| Factor | Favors making when… | Favors buying when… |
|---|---|---|
| Capacity | The equipment and people are underused | The plant is at capacity and the hours have a better use |
| Quality | The process is hard to specify or control at a supplier | A specialist supplier has better process capability |
| Lead time and flexibility | Short lead times or frequent changes matter | Demand is steady and well forecast |
| Supply risk | Few qualified suppliers exist | Several capable suppliers compete |
| Know-how | The part embodies process knowledge you want to keep | The part is a commodity |
A narrow cost gap, like the $1,600 in the example, should not decide the question on its own. If the hours freed by buying could make a higher-margin part, capacity can matter more than unit cost. If the supplier would be a single source, factor in that risk, and for overseas quotes compare options in our reshoring vs nearshoring guide.
Common mistakes
- Using full absorbed cost. Allocated overhead that stays either way makes in-house parts look too expensive.
- Comparing a quote to last year’s volume. Quotes are volume-dependent; compare at the volume you will buy.
- Leaving out landed costs. Freight, duty, inspection and extra inventory can close the gap on a low quote.
- Ignoring transition costs. Supplier qualification, first-article inspection, tooling transfer and a ramp-up buffer are real one-time costs.
- Treating the decision as permanent. Volumes and prices change. Revisit major make vs buy calls when either moves materially.
If you are weighing several parts or a larger sourcing change, our operations consulting and supply chain services can help you build the cost model and the decision criteria with your own data.
Weighing a make-or-buy decision?
We help manufacturers build a relevant-cost comparison, test the break-even and score the factors that numbers miss.
Related reading: capacity planning in manufacturing, to check you have the machine hours to make it.
Frequently asked questions
What costs belong in a make vs buy analysis?
For making: material, direct labor, variable overhead and any fixed cost that would end if you stopped making the part. For buying: the supplier price plus freight, duty, inspection and the cost of any extra inventory the supplier’s lot sizes require.
Should allocated overhead be included?
Only the part that would actually go away. Rent, shared equipment and management that stay whether you make or buy should be left out, or the make option will look more expensive than it is.
What is the make vs buy break-even volume?
It is the annual volume at which both options cost the same: avoidable fixed cost ÷ (landed buy cost per unit − variable make cost per unit). Above it, making is cheaper; below it, buying is cheaper.
Is make vs buy only about cost?
No. Capacity, quality, lead time, supplier risk and protection of know-how can outweigh a small cost difference. Score them alongside the numbers.