Takt time vs cycle time vs lead time

Takt time is the pace you need to match customer demand: available working time ÷ customer demand. Cycle time is how long a station or process actually takes to finish one unit. Lead time is how long the customer waits, from order to delivery. Takt is a target set by demand. Cycle time and lead time are measured on your floor.

The rule that ties them together: every station’s cycle time must be at or below takt, or the line cannot keep up with demand in the hours you work. Lead time includes all the waiting between steps, so it is longer, often much longer, than the sum of the cycle times. Below are the formulas, a worked example of a line that misses takt, what to do about it, and when takt is the wrong tool.

The formulas

Takt time

Takt time = available working time ÷ customer demand

Available working time is the time the line is staffed and meant to run in the period, after breaks and lunch. Customer demand is the units you need to ship in the same period. Use the same period for both: a shift, a day or a week.

Cycle time

Cycle time = time a station takes to finish one unit

Measure it by timing the station from the start of one unit to the start of the next, over several units, including loading and unloading. For a batch process, divide the batch time by the units in the batch. The cycle time of a line is the cycle time of its slowest station.

Lead time and throughput time

Lead time = delivery date − order date

Customer lead time runs from the customer’s order to delivery. Manufacturing lead time, also called throughput time, runs from the release of the order, or the start of the first operation, to the finished unit. Both include the time a part waits between operations. For a line that runs steadily, there is a quick check:

Throughput time ≈ work in process ÷ output rate

Takt, cycle and lead time compared

Takt timeCycle timeLead time
Question it answersHow fast must we finish one unit to meet demand?How fast do we finish one unit?How long does the customer wait?
Set byCustomer demand and the hours you workWork content, method, machine speedQueues, batch sizes, materials and cycle times
FormulaAvailable time ÷ demandTime per unit at a stationDelivery date − order date
Usual unitSeconds or minutes a unitSeconds or minutes a unitDays or weeks
Changes whenDemand or the work schedule changesYou change the station or the methodYou cut waiting, batch sizes or cycle times

Worked example: a welded frame line

Example inputs, not real data. A four-station line making a welded steel frame on one 8-hour shift a day. The numbers are made up to show the method.

The shift is 480 minutes, with a 30-minute lunch and two 15-minute breaks, so available working time is 420 minutes, or 25,200 seconds. Customers need 350 frames a day.

Takt time = 25,200 seconds ÷ 350 frames = 72 seconds a frame

StationCycle time (seconds)Against takt of 72 seconds
1. Cut5517 under
2. Weld8513 over
3. Grind6012 under
4. Assemble and pack702 under
Total work content270

Weld is the only station over takt, so it sets the pace of the whole line. At 85 seconds a frame the line makes 25,200 ÷ 85 = 296 frames a shift, 54 short of demand. Speeding up the other three stations adds nothing: the station before weld just builds a pile in front of it, and the stations after it wait.

Now the lead time. Say 60 frames sit in the line on a normal day, most of them in front of weld. Throughput time ≈ 60 frames × 85 seconds = 5,100 seconds, or 85 minutes. Each frame is worked on for 270 seconds, 4.5 minutes, of that. If an order also waits 5 working days for a slot on the schedule and 1 day for packing and shipping, the customer’s lead time is about 6 working days, of which 4.5 minutes is work.

Four ways to close the gap

When a station’s cycle time is over takt, you have four main choices. Work out each one before you pick.

  1. Overtime at weld. 350 frames × 85 seconds = 29,750 seconds, or about 496 minutes. That is 76 minutes a day more than the 420 available, and the stations after weld must stay too, or work from a buffer the next morning. Fine for a few weeks; as a permanent fix it wears people out and costs the overtime premium.
  2. A second shift. It doubles available time to 840 minutes. Takt for 350 frames becomes 144 seconds, well above every station. Useful if demand is going to grow; more than you need for a 54-frame gap.
  3. Balance the line. Move work from weld to a station with slack. If 15 seconds of tube-end prep moves from weld to cut, weld drops to 70 seconds and cut rises to 70. Every station is now under 72 seconds, and the line can make 25,200 ÷ 70 = 360 frames a shift with no new equipment.
  4. Add a welder or a machine. Two welders working in parallel give an effective cycle time of 85 ÷ 2 = 42.5 seconds. That buys room for growth, at the price of a wage or a second welding cell.

You can also send part of the volume out. Compare the cost per frame of each option, including the overtime premium and the price of buying outside, before you decide. In the Lab’s production planning software, the Scenario simulator runs the whole schedule again with overtime, an added shift, an extra machine or outsourcing, and shows the cost and the orders that would still be late.

How many operators or stations you need

Minimum stations or operators = total work content ÷ takt time

For the frame line: 270 seconds ÷ 72 seconds = 3.75, so you need at least 4 stations. Always round up. Four stations are enough only if the work splits evenly, and balance efficiency tells you how evenly it splits:

Balance efficiency = total work content ÷ (number of stations × slowest cycle time)

Before the change: 270 ÷ (4 × 85) = 79%. After moving the tube-end prep: 270 ÷ (4 × 70) = 96%. If demand rises to 420 frames a day, takt falls to 25,200 ÷ 420 = 60 seconds, and you need 270 ÷ 60 = 4.5, so 5 stations or operators. To run your own numbers, use the free takt time calculator.

Common mistakes

Using calendar time instead of working time

Takt for a line that runs one shift, five days a week, comes from those hours, not from 24 hours a day, 7 days a week. For the frame line, a week of 1,750 frames over 2,100 working minutes gives 72 seconds. Divide the calendar week of 10,080 minutes instead and you get 346 seconds, a pace 4.8 times too slow.

Forgetting breaks and changeovers

Breaks come out of available time. Changeovers often stay in, since takt describes demand, but they still eat into the time the line can run. If the frame line loses 30 minutes a day to changeovers, each station has to run at (25,200 − 1,800) ÷ 350 = 66.9 seconds or better to keep up, not 72. Shorter changeovers give that time back; see setup time reduction.

Mixing up cycle time definitions

Cycle time means different things to different people: machine cycle time (door closed to door open), operator cycle time (one full round of the operator’s work), and, in some offices, the time an order takes end to end. When you compare with takt, use the time between finished units at the station, including load and unload. Write the definition at the top of the sheet.

Using demand from the wrong period

Takt is only as good as the demand figure. Use what you need to ship in the weeks the takt will apply, including any backlog you plan to catch up, not last year’s monthly average. Take it from your demand planning process so production and sales work from the same number.

When takt time does not fit

Takt works best when the same product, or a family of similar products, runs through the same stations day after day. In a high-mix job shop it fits poorly: each job has its own routing, its own times and its own due date, so there is no single pace to match.

In a job shop, plan in hours instead. Add up the hours each work center needs by week, set them against the hours it has, and schedule jobs against finite capacity. Our guide to capacity planning in manufacturing walks through that, and how to find the bottleneck shows how to spot the work center that limits output. Takt can still help inside a job shop, for a repeat product family run in a cell.

That is how the Lab’s Production Planning works: each operation goes on a machine of its work center without overlapping other jobs, the Capacity planning page shows load by week, and the bottleneck is named.

Is your line short of takt, or short of hours?

Production Planning shows the load on each work center by week and lets you test overtime, a shift or a machine before you commit.

Frequently asked questions

What is the difference between takt time and cycle time?

Takt time is the pace demand requires: available working time divided by customer demand. Cycle time is the pace you actually achieve at a station. If cycle time is longer than takt, you cannot meet demand in the hours you work.

How do you calculate takt time?

Divide the available working time in a period by the units customers need in that period. For example, 25,200 seconds a shift divided by 350 units is 72 seconds a unit.

Is lead time the same as cycle time?

No. Cycle time is the time to finish one unit at a station. Lead time runs from order to delivery and includes all the waiting between operations, so it is usually much longer.

What happens when cycle time is greater than takt time?

The line falls behind demand on every unit. You can add overtime or a shift, move work to stations with slack, add a person or machine at the slow station, or send work out.

Does takt time work in a job shop?

Not well, because each job has its own routing and times. Plan a job shop in hours by work center against finite capacity, and use takt only for repeat product families.