Available to promise (ATP) is the quantity you can still promise to customers from stock on hand and scheduled supply, after existing orders. Capable to promise (CTP) goes one step further: it also checks free production or supplier capacity and lead time, to see whether you could make or buy more, and by when.
In short, ATP vs CTP is a question of where the answer comes from. ATP looks at material you have or have on order. CTP looks at what you could still produce. Stocked items usually need ATP, and made-to-order work needs CTP. The rest of this post shows both with numbers.
ATP vs CTP at a glance
| Available to promise (ATP) | Capable to promise (CTP) | |
|---|---|---|
| Question it answers | How many units can I commit from supply I already have or have ordered? | Can I make or buy this, and by what date? |
| Looks at | On hand, open purchase or production orders, committed customer orders | Everything in ATP plus free capacity at the bottleneck, material lead times and routing time |
| Best for | Stocked, make-to-stock and assemble-from-stock items | Make-to-order, engineer-to-order and items with no stock to promise |
| Output | A quantity by period, and the first period that covers a request | A completion date, plus the capacity it will use |
| Main weakness | Ignores whether you could make more | Needs reliable routings, capacity data and lead times |
What is available to promise?
ATP is a count of uncommitted supply by period. In each period you take supply, subtract customer orders already promised, and carry on until the next supply arrives. Our guide to available to promise, with the formula and an example covers the basics, and the available to promise calculator will run your own numbers.
ATP in a period = supply in the period (on hand in period 1, plus scheduled receipts) − committed orders, up to the next supply
That is the discrete form. For quoting, a running version works better, because it stops you promising the same units twice. It is shown below.
What is capable to promise?
Capable to promise asks what ATP cannot: if stock and open orders do not cover the request, could we produce it, and when? To answer, it checks three things in order:
- Material: when the components can arrive, given supplier lead times and any open orders.
- Capacity: how many free hours the bottleneck work center has in each week, after work already committed.
- Routing time: the time the later steps take, such as assembly, test and packing.
The result is the earliest date you can ship. The date is only as good as the data behind it. If routing times or work center hours are guesses, so is the promise. Finding the constraint is the first job: see how to find the bottleneck in production.
When to use ATP and when to use CTP
- Stocked items and distribution: use ATP. The customer wants a quantity from shelves or a coming receipt, and capacity is not the limit.
- Make-to-order and engineer-to-order work: use CTP. There is no stock to promise, and the date depends on material and machine time.
- Mixed shops: use ATP first. If stock and open supply cannot cover the order, run a CTP check on the bottleneck before you give a date.
ATP is a standard output of MRP and the master production schedule. CTP needs capacity data on top, which is why it sits closer to production planning software than to a basic inventory system.
Worked example: ATP by period with look-ahead
Example inputs, not real data. One stocked item with 100 units on hand. Open purchase orders bring 120 units in weeks 3 and 6. Committed customer orders by week are 40, 30, 50, 40, 20 and 30 units.
| Week | Open PO receipts | Committed orders | Cumulative supply | Cumulative orders | Cumulative available | Cumulative ATP (look-ahead) | ATP in the week |
|---|---|---|---|---|---|---|---|
| 1 | 0 | 40 | 100 | 40 | 60 | 30 | 30 |
| 2 | 0 | 30 | 100 | 70 | 30 | 30 | 0 |
| 3 | 120 | 50 | 220 | 120 | 100 | 40 | 10 |
| 4 | 0 | 40 | 220 | 160 | 60 | 40 | 0 |
| 5 | 0 | 20 | 220 | 180 | 40 | 40 | 0 |
| 6 | 120 | 30 | 340 | 210 | 130 | 130 | 90 |
Cumulative supply is 100 on hand plus receipts so far: 100, 100, 220, 220, 220, 340. Cumulative available is supply minus cumulative orders. Then the look-ahead rule applies: the cumulative ATP for a week is the lowest cumulative available figure from that week to the end of the horizon. That is why week 1 shows 30, not 60. Week 5 has only 40 available, and anything promised earlier comes out of it.
Cumulative ATP in week t = the minimum of cumulative available in weeks t to the last week
Check the total: weekly ATP adds up to 30 + 10 + 90 = 130, which equals total supply of 340 less total orders of 210. As a second check, discrete ATP agrees: week 1 is 100 − (40 + 30) = 30, week 3 is 120 − (50 + 40 + 20) = 10, and week 6 is 120 − 30 = 90.
Now quote three requests. 25 units in week 1: yes, since cumulative ATP is 30. 40 units by week 3: yes, since cumulative ATP is 40. 50 units by week 2: no, since cumulative ATP is 30 in week 2, and the first week that covers 50 is week 6. A request of 100 units for week 3 would look fine against the 100 in the cumulative available column, but promising it would leave week 5 short by 60 (40 − 100). That is the mistake the look-ahead prevents.
The order promising software page shows how this works with open orders in the Lab.
Worked example: a CTP check on the bottleneck
Example inputs, not real data. A customer wants 60 units of a made-to-order part with no stock. The bottleneck is the CNC area: two machines, 40 hours each a week, so 80 hours. Each unit needs 0.5 hours there. Components take 10 working days to arrive, so work starts in week 3. Assembly and test take one week and have spare capacity.
| Week | CNC hours available | Already committed | Free hours | Cumulative free from week 3 |
|---|---|---|---|---|
| 1 | 80 | 62 | 18 | not usable, no material |
| 2 | 80 | 70 | 10 | not usable, no material |
| 3 | 80 | 75 | 5 | 5 |
| 4 | 80 | 40 | 40 | 45 |
| 5 | 80 | 20 | 60 | 105 |
The order needs 60 × 0.5 = 30 hours. From week 3 the free hours are 5 in week 3 and 40 in week 4, so 45 in total, which covers 30. Week 3 takes the first 10 units (5 hours), and week 4 takes the remaining 50 units (25 hours). The CNC work finishes in week 4. If material arrived at once, weeks 1 to 3 would offer 18 + 10 + 5 = 33 free hours and the work would finish in week 3. The material lead time, not the machines, costs a week here.
Assembly and test take week 5, so the earliest ship date is the end of week 5. Once you accept the order, book it: week 3 CNC load goes to 80 hours, week 4 goes from 40 to 65 hours. If you do not book it, the next quote counts the same hours again.
How to tell a customer a date
- Quote from ATP first. If the quantity is covered, give the date of the first period where cumulative ATP covers it.
- Check CTP when ATP falls short. Give the CTP date only if the data behind it is current.
- Add a buffer where load is high. The CNC area above is 94% loaded in week 3 (75 of 80 hours), so a delay there moves the date. Quote a safe date, and treat the earliest one as your target.
- Confirm supplier dates. A supply date in the plan is a promise from someone else. See how to get suppliers to confirm dates.
- Reserve at once. A promise that is not booked against supply or capacity is a guess.
Common mistakes
- Promising from on hand and forgetting committed orders in later weeks.
- Skipping the look-ahead, so one early promise empties a later week.
- Counting open purchase orders at the date the supplier first gave, not the date they now confirm.
- Using CTP with routing times or work center hours nobody has checked.
- Counting material that is already reserved for another job, which is also what a clear to build report exists to catch.
- Quoting a CTP date without reserving the capacity.
How Statadventure fits
The Statadventure Optimization Lab calculates available to promise from stock and open purchase orders, which suits stocked items and mixed shops. CTP needs capacity and routing data, so it relies on the load view from the production planning pages (MPS, finite scheduling and OEE), which are a separate plan. The free live demo lets you try order promising on sample data. If you are still choosing a system, compare MRP software for small manufacturers and inventory planning software. A reliable promise also starts with a forecast, so see demand planning software.
Promise dates you can keep
The Statadventure Lab shows available to promise from stock and open orders, on sample data in the live demo.
Frequently asked questions
What is the difference between available to promise and capable to promise?
Available to promise counts supply you already have or have ordered, less committed orders. Capable to promise also checks free capacity and lead times to see whether you could make more, and by when.
What is capable to promise?
Capable to promise is a check of whether you can produce or buy a requested quantity by a date. It tests material arrival, free hours at the bottleneck work center and the time of later steps, then gives the earliest ship date.
When should I use ATP vs CTP?
Use ATP for stocked items, where the answer is in on-hand stock and open orders. Use CTP for make-to-order and engineer-to-order work, or when ATP cannot cover the request and you must test capacity.
How do you calculate available to promise?
Take on hand plus scheduled receipts, subtract committed customer orders, and carry the running total forward. Use cumulative ATP with look-ahead, so a promise in one week does not leave a later week short.
Sources: the worked examples use made-up numbers, and the arithmetic is shown so you can check it. For the formula and a longer example, see our available to promise guide.