Clear to build: what it means and how to build the report

Clear to build means you have every component needed to start and finish a production order. A clear-to-build report tells you how many units you can make right now, and which part is holding back the rest.

How to calculate clear to build

Buildable units for a component = available quantity ÷ quantity per unit, rounded down

Clear to build = the lowest buildable figure across all components

Available quantity is stock on hand plus any receipts you trust to arrive before the build starts.

A worked example

You plan to build 100 units of a product with four components.

ComponentQty per unitRequiredOn handConfirmed POAvailableShortBuildable
Frame110012001200120
Motor11006020802080
Bracket440050005000125
Cable22001501002500125

You are clear to build 80 units. The motor is the constraint, and you are 20 short. Chasing the frame, bracket or cable would not help, so the buyer’s effort should go to the motor.

What a useful report includes

  • Product, order number and build date
  • Quantity planned and quantity clear to build
  • Each component’s required, on-hand, on-order and short quantities
  • The constraining component and its supplier
  • The promised date of the next receipt, and whether the supplier confirmed it

Confirmed dates matter because an unconfirmed purchase order is only a hope. See how to get purchase orders confirmed.

The hard part: shared components

When two products use the same part, you cannot count the same stock twice. Allocate it in priority order, usually by due date or customer, and then recalculate. A spreadsheet works for a handful of orders and gets painful after that.

How to use it

  1. Run it before you release work to the floor.
  2. Start only what is fully clear, so you do not fill the floor with half-finished units.
  3. Give buyers the list of constraining parts, sorted by what they block.
  4. Review it daily when shortages are common.

The clear-to-build process, step by step

  1. Pick the orders to check. Take those due to start in the next one to two weeks, in start-date order.
  2. Count the stock you can really use. On hand, less anything quarantined or rejected, less what earlier orders have already claimed.
  3. Work out what each order needs by multiplying its quantity through the bill of materials.
  4. Give components to orders in start-date order, so a later order cannot take parts an earlier one needs.
  5. Mark each order clear, partly clear (with the units it can build) or short, and name the part that limits it.
  6. Act on the shortages. Expedite the purchase order, use an approved substitute, build a partial quantity or move the order.
  7. Run it again when receipts arrive, at least daily for this week’s orders.

Clear to build software: what to look for

A spreadsheet can check one order. The work gets hard when many orders share parts. Whatever tool you use should:

  • give shared components to orders in sequence, not check each order as if it were alone;
  • show the limiting part for each order and when its next receipt is due;
  • show which products or customer orders each shortage blocks;
  • let you choose whether open purchase orders count, and use their dates when they do;
  • work from the files you already have: bills of materials, stock and open orders.

The Statadventure Lab does this in two places. Materials planning, on the Planner and Growth plans, shows clear-to-build and the products each shortage blocks; see MRP software for small manufacturers. Production Planning, at $99 a month, marks every production order ready, waiting or short in the order the schedule will run them.

Where it fits

Clear to build is the most practical output of MRP. If your system cannot produce it, read our guide to MRP software for small manufacturers. The Statadventure Optimization Lab shows clear-to-build and which products each shortage blocks, on the Planner and Growth plans.

See clear-to-build on a sample company

The live demo needs no account. Use the sample company or load your own files, which stay in your browser tab.

Related reading: production scheduling that checks materials order by order.

Frequently asked questions

What does clear to build mean?

That all the components needed for a build are available, so production can start and finish without waiting for parts.

What is a clear-to-build report?

A report that shows, for each planned build, how many units can be made with available material, and which component limits the rest.

Should clear to build include parts still on order?

Only receipts you trust to arrive before the build starts. Many teams show one figure from stock on hand and a second that includes confirmed orders.