Free machine capacity and utilization calculator

Work out the hours a group of machines can really deliver in a week, set this week’s work against it, and see the capacity utilization and how many hours you are over or under. Enter the load as total hours, or as units and run times with setups. It runs in your browser. Nothing you enter is stored or sent.

Machines that can run the same work, such as one work center.

Hours a machine is staffed and can run in one shift. Take out breaks if the machine stops for them.

Filled in as 85% to start. Replace it with your own figure. It covers small stops, slow running and other losses that keep a machine from producing in every scheduled hour.

All machines together, in the hours they would otherwise run. Enter 0 if none.

The load this week

How do you want to enter the load?

Standard hours for all the jobs due on these machines this week, setups included. Efficiency is applied to capacity only, so do not add an allowance here.

How machine capacity is calculated

Capacity starts with the hours the machines are staffed, less planned maintenance, and is then reduced by efficiency to the hours they really produce. Load is the work due in the same week at standard times. Utilization compares the two.

Gross machine hours = machines × shifts per day × hours per shift × working days per week

Available capacity = (gross machine hours − planned maintenance) × efficiency

Load = hours of work, or (units × run time per unit + setups × setup time) ÷ 60

Utilization = load ÷ available capacity × 100

Hours over capacity (or to spare) = load − available capacity

Extra shifts needed = hours over ÷ (hours per shift × efficiency), rounded up

Over 100% means the week’s work does not fit. Run the calculator for the machine group you think is the bottleneck first. The guide to capacity planning in manufacturing shows how to do this week by week and what to change when load runs over.

A worked example

Example inputs, not real data

A work center has 3 machines running two 8-hour shifts, 5 days a week, with 6 hours of planned maintenance across the three machines this week. Efficiency is left at the 85% assumption. This week’s orders need 1,300 units at 9 minutes each, plus 12 setups at 45 minutes each.

  • Gross machine hours = 3 × 2 × 8 × 5 = 240 hours
  • Available capacity = (240 − 6) × 85% = 234 × 0.85 = 198.9 hours
  • Load = (1,300 × 9 + 12 × 45) ÷ 60 = (11,700 + 540) ÷ 60 = 204 hours
  • Utilization = 204 ÷ 198.9 = 102.6%
  • Over capacity by 204 − 198.9 = 5.1 hours

One extra 8-hour shift on one machine adds 8 × 0.85 = 6.8 hours, enough to cover the 5.1. Taking 10 minutes off each of the 12 setups would free another 2 hours. Use the Load example button above to run these figures, and see setup time reduction (SMED) for ways to shorten changeovers.

Frequently asked questions

What efficiency should I use?

Use your own figure if you track one: hours of work produced at standard times divided by the hours the machines were scheduled. The 85% filled in is only a starting assumption. If you track OEE and your run times are ideal times, OEE is a reasonable figure to use.

Is capacity utilization the same as OEE?

No. Utilization compares the work you have with the hours you can supply. OEE measures how well a machine runs during the time it is scheduled. A machine can be fully loaded and still have a low OEE.

What can I do if load is over capacity?

Add hours with overtime or an extra shift, move work to another machine or another week, cut setup time, or send some work to an outside supplier. Check the bottleneck first: extra hours anywhere else do not raise output.