Statadventure Lab · Production schedule
Production scheduling software with a finite-capacity Gantt chart
Put every operation on a real machine, inside real shifts, and see which orders finish late before the week starts. The Lab’s Production schedule builds the sequence, lets you drag a job where you want it, and replans the rest around your change. It is made for job shops and small plants, at $99 a month.
What finite capacity means here
An infinite-capacity plan assumes every work center can absorb any load, so overloads only show up on the floor. A finite schedule books real hours on real machines; our article on finite vs infinite capacity scheduling covers the difference. The Lab’s schedule holds to five constraints.
- One job at a time on a machine. Operations never overlap on a machine, though a short one can use a gap between two jobs.
- Working hours only. Each work center has shifts, hours a shift, overtime and working days. Unfinished work pauses at the end of the day and resumes at the next working day’s start hour.
- Planned maintenance is blocked out, for one machine or for every machine in a work center.
- Setups follow the changeover family. A job that follows the same family on that machine skips its setup, or keeps the share you set in Settings.
- The routing order holds. Each operation waits for the one before it, plus any wait time, and the first waits for the order’s materials.
The scheduler tries every machine in the operation’s work center and uses the one that would finish it soonest. The time an operation takes is:
hours = (setup + run per unit × units left) ÷ efficiency
Example inputs, not real data. A step has 1.5 setup hours a batch and 0.05 run hours a unit, 400 units are left, and the work center runs at 85% efficiency. It needs (1.5 + 0.05 × 400) ÷ 0.85 = 21.5 ÷ 0.85 ≈ 25.3 hours. If the job before it on that machine is in the same changeover family, the setup is skipped: 20 ÷ 0.85 ≈ 23.5 hours. On a work center with two 8-hour shifts, 25.3 hours is about 1.6 working days.
Units left falls as people report progress, so bars shorten as work gets done. To shorten them further, see our guide to setup time reduction.
Automatic sequencing: four rules, then improvement
Choose “Automatic” and the Lab builds a full schedule with each of four production scheduling rules.
- Priority, then due date. Priority 1 goes first, then 2, and so on to 5. Ties go to the earlier due date.
- Earliest due date. The order due first goes first.
- Critical ratio. Time until the due date ÷ hours of work still to do. The lowest ratio goes first.
- Least slack. Time until the due date − hours of work still to do. The least slack goes first.
Each schedule is scored on priority-weighted late days first, then changeover hours. The Lab keeps the best, then swaps neighboring orders and moves late orders forward while the score keeps falling. It is a heuristic: it finds a good sequence in milliseconds, with no proof that a better one does not exist. You can also run a single rule on its own. Work already running stays on its machine and goes first. Every equation is on the Lab’s Metrics page.
Drag a job to pin it
You know things the data does not, like the operator who is out on Friday. Drag a bar to another time or machine and that operation is pinned: it keeps its machine and start time, and everything else is replanned around it. Pinned bars are marked, and “Clear my changes” removes your pins.
When a pin cannot work, the conflict is listed above the chart:
- Two operations on the same machine at the same time, or one pinned over planned maintenance.
- An operation pinned to start before the operation ahead of it in the routing finishes.
- An operation pinned to start before its materials arrive.
Four ways to read the schedule
- By machine. Bars colored on time, at risk or late, with changeovers and maintenance shown, over one, two or four weeks, or everything.
- By order. Each order’s operations on one row, from first to last.
- This week by day. What each work center works on each day.
- Dispatch list. Every operation for one work center, by machine, with start, end, units and hours, plus a CSV download of the schedule.
A batch size table compares your current batch with the economic production quantity for each product that has a forecast and an item cost. Load by week and the bottleneck are on Capacity planning; our guide on how to find the bottleneck explains why that work center comes first.
Materials checked in schedule order
Before an order that has not started can run its first operation, the Lab gives it components in schedule order, so the order that runs first has first claim.
- Stock on hand.
- Open purchase orders, counted as available one day after their due date.
- Open production orders that make the component.
An order already under way is taken to have its materials. A component nothing covers is short. If it has a lead time, the order waits for a purchase placed today, and the component goes on the list to buy.
What-if scenarios on the same plan
The Scenario simulator copies the plan, applies one or more changes and reschedules everything. It starts from the plan’s own sequence, so the difference comes from the change, not from a new search. Plan and scenarios sit side by side: late orders, late days, the last finish date, components short, the bottleneck, cost, revenue and profit. A scenario that only adds a shift, overtime, Saturdays or a machine at one work center can be made the plan by someone allowed to approve it.
When a machine breaks down
To weigh your options, run the “A machine breaks down” scenario. Pick the work center, the machine, when it stops and for how many days, and see which orders slip.
Once it has happened, record the stop on the Overview. It counts against that work center’s availability in OEE, but it does not block the machine in the schedule by itself. For a repair of known length, add planned maintenance on Capacity planning and the schedule moves work around it, or drag the affected operations to another machine.
Data you need
Three Excel or CSV files give you a first schedule, and Settings & integrations has a template for each.
| File | Columns it needs | Useful extras | On import |
|---|---|---|---|
| Work centers | work_center, machines | shifts, hours_per_shift, days_per_week, efficiency_pct, machine_rate_per_hour | Replaces the list |
| Routings | sku, work_center, and a run time as hours a unit, minutes a unit or units an hour | operation_seq, setup_hours, changeover_family, wait_hours | Replaces the routings |
| Production orders | order number, sku, qty | due, priority (1 highest to 5), customer, status | Adds new orders and updates those with the same number; never deletes |
Shop-floor reports, machine stops and inspections are optional files you can add later. Items, bills of materials, stock and open purchase orders come through the Lab’s own import. Still scheduling in a spreadsheet? Our free production schedule template helps you write the work centers, routings and orders down first.
Price
The Production schedule is one of twelve pages in Production Planning: $99 a month or $950.40 a year on its own, or a $99 monthly add-on for Basic, Planner and Growth teams. The full table is on our production planning software page.
Limits to know
- Operators are not a scheduling constraint. Skill hours are compared with your people week by week and a gap is flagged, but no job waits for a person.
- No live machine or sensor feeds. Progress and stops come from people or from files, such as an MES export.
- No e-mailed or scheduled reports. You open the schedule in the Lab and download it.
Drag a job on a sample plant
In the live demo, the Production schedule runs on a sample pumps and valves plant, with no account needed.
Frequently asked questions
What is finite-capacity scheduling?
Scheduling that books each operation on a machine for real hours, so a machine never holds two jobs at once or works outside its shifts. Infinite-capacity planning ignores those limits and lets the load pile up.
Does automatic sequencing find the best possible schedule?
No. It tries four rules, keeps the best and improves it by moving orders. That is fast, but it is a heuristic, not a proven optimum.
What happens when I drag a job on the Gantt chart?
That operation is pinned to the machine and start time, and everything else is replanned around it. A pin that overlaps other work or maintenance, or starts before the step ahead of it or its materials, is listed as a conflict.
Does the schedule plan operators as well as machines?
No. Machines are scheduled and people are checked: if a week needs more hours of a skill than your people with that skill have, the shortfall is flagged.
What data do I need for a first schedule?
Three Excel or CSV files: work centers with the number of machines, routings with run times, and production orders with a product and quantity.