Master production schedule (MPS): how to build one, with an example

A master production schedule (MPS) is the plan of how many of each end item, or product family, you will finish in each period, usually each week, over the coming weeks and months. It sits between the sales and operations plan and material requirements planning (MRP): it turns demand into quantities you can build, and MRP then works out the components and materials those quantities need.

An MPS is a statement of supply, not of demand. You start from the forecast and the customer orders, take account of stock, safety stock, lot sizes and time fences, and get three calculated rows for every week: the quantity to make, the projected available balance, and the quantity still available to promise to new customers.

MPS vs forecast vs production schedule

ForecastMaster production scheduleProduction schedule
What it saysWhat customers will probably orderWhat you will finish, and in which weekWhich machine runs which order, at what hour
LevelItems, families, customersEnd items or familiesProduction orders and operations
Time bucketWeek or monthWeekHour or minute
CapacityNot consideredChecked roughly at key work centersChecked machine by machine
OwnerDemand planning and salesMaster scheduler or plannerScheduler or supervisor

The forecast can move freely. The MPS should not follow every move, because purchase orders, production orders and promises to customers hang off it. For how the forecast itself is built, see the demand planning process. For the step below the MPS, see production planning vs production scheduling.

What goes into an MPS

  • Forecast by week, for each item or family on the MPS.
  • Customer orders already booked, in the week they are due.
  • Stock on hand at the start.
  • Safety stock, the balance you do not want to plan below. The safety stock formula guide compares three ways to set it.
  • Lot size: a fixed quantity, a multiple, or lot for lot.
  • Time fences that limit what can change in the near weeks.
  • Hours per unit at key work centers, for the rough-cut capacity check.

The MPS rows and how to calculate them

Each week of the MPS has five rows. Forecast and customer orders are inputs. The other three are calculated:

Requirement for the week = the larger of forecast and customer orders

Projected available balance = last week’s balance + MPS quantity − requirement for the week

In week 1, last week’s balance is the stock on hand. When the balance would fall below safety stock, schedule an MPS lot. If one lot is not enough, schedule two.

ATP in week 1 = stock on hand + MPS quantity − customer orders until the next MPS lot

ATP in a later week with a lot = MPS quantity − customer orders from that week until the next lot

Available to promise (ATP) is shown only in week 1 and in weeks with an MPS lot. It uses customer orders, not the forecast, because it answers a sales question: how much of this supply is not yet promised to anyone? If a later week’s ATP comes out negative, take the shortfall from the ATP of the lot before it.

Worked example: a six-week MPS

Example inputs, not real data. One end item, pump P-200. 60 units on hand at the start, safety stock of 20 units, made in lots of 100. Forecast and customer orders as in the table; week 5 has a seasonal peak.

Week123456
Forecast5050606015070
Customer orders55403020105
Projected available balance10555953585115
MPS quantity100—100—200100
Available to promise65—50—19095

The projected available balance, week by week:

  • Week 1: the requirement is 55, the larger of 50 and 55. 60 − 55 = 5 is below safety stock, so a lot of 100 goes in: 5 + 100 = 105.
  • Week 2: 105 − 50 = 55. No lot needed.
  • Week 3: 55 − 60 = −5. A lot of 100 brings it to 95.
  • Week 4: 95 − 60 = 35.
  • Week 5: 35 − 150 = −115. One lot would give −15, still below 20, so two lots: −115 + 200 = 85.
  • Week 6: 85 − 70 = 15, below 20. One lot brings it to 115.

Available to promise:

  • Week 1: 60 on hand + 100 − orders in weeks 1 and 2 (55 + 40) = 65.
  • Week 3: 100 − orders in weeks 3 and 4 (30 + 20) = 50.
  • Week 5: 200 − 10 = 190.
  • Week 6: 100 − 5 = 95.

Suppose a customer asks for 70 units in week 2. Week 1’s ATP of 65 covers weeks 1 and 2, so you can promise 65 for week 2 and the other 5 for week 3, out of week 3’s ATP. Or offer all 70 in week 3. Add the ATP figures up as you go (65, 65, 115, 115, 305, 400) and you get the cumulative ATP, the same answer the look-ahead method in our available to promise guide gives.

Time fences: frozen, slushy and liquid

Changing the MPS in week 1 costs more than changing it in week 6: material is bought, work has started, and other orders were sequenced around it. Time fences make that explicit. In the example:

  • Frozen (weeks 1 and 2): no changes without a deliberate decision by whoever owns the plan, usually the plant or operations manager.
  • Slushy (weeks 3 and 4): changes are allowed if material and capacity are there, and the planner weighs each one.
  • Liquid (week 5 on): open. New demand can move lots freely, and new lots can be planned.

Many planning systems mark these zones with two named fences, the first often at the end of the frozen zone and the second at the end of the slushy zone. Inside the demand time fence, only customer orders count and the forecast is ignored. Inside the planning time fence, the system does not create or move MPS lots on its own; the master scheduler does it by hand. If you count only customer orders inside the demand time fence, the balances and even the lots can come out different from the table above, so pick one rule and apply it every week.

The rough-cut capacity check

An MPS the plant cannot build is a wish list. Before you release it, multiply each week’s MPS quantity by the hours a unit needs at your key work centers and compare the result with the hours available. This is rough-cut capacity planning. In the example, each P-200 needs 0.3 hours in assembly, and assembly has 35 hours a week left for P-200 after other products.

Week123456
MPS quantity100—100—200100
Assembly hours needed (× 0.3)3003006030
Hours available353535353535
Over (+) or under (−)−5−35−5−35+25−5

Week 5 is 25 hours over, and week 4 has 35 hours free. Move one lot of 100 from week 5 to week 4, and assembly needs 30 hours in weeks 1, 3, 4, 5 and 6, all within the 35 available. The projected balance in week 4 rises from 35 to 135, which is the cost of the fix: 100 more units held for a week. Week 5 still ends at 85, and ATP becomes 65, 70, 80, 90 and 95 in weeks 1, 3, 4, 5 and 6. Week 4 is in the slushy zone, so check that the components can arrive a week earlier before you commit.

How often to update the MPS

Update it weekly, at a fixed time, once the week’s new orders are in. Drop the week that ended, add a new week at the end, recalculate, and run the rough-cut check again. Review the families, the time fences and the lot sizes monthly, when the forecast and the sales and operations plan change.

Plan far enough ahead to cover your cumulative lead time: the longest chain of purchasing and production time, from ordering the first component to finishing the end item. An MPS shorter than that cannot tell purchasing what to order in time.

Common mistakes

  • Copying the forecast into the MPS. The MPS should net out stock, respect lot sizes and safety stock, and fit capacity. A copy of the forecast does none of that.
  • An MPS over capacity. If the rough-cut check fails week after week, the floor will decide what really gets made, and MRP will order material for a plan nobody follows.
  • Changing the frozen weeks every week. Each change ripples into purchase orders and the schedule. If the frozen zone is never frozen, shorten it to what you can hold, and then hold it.
  • Promising from stock on hand instead of ATP. Stock on the shelf may already belong to a customer whose order is due next week.
  • Planning at the wrong level. If you assemble to order from a few modules, an MPS of every finished configuration becomes huge and inaccurate. Master-schedule the modules or the family, and leave the final configuration to a final assembly schedule.
  • Buffering twice. Padding the forecast and also planning to safety stock inflates the MPS. Keep the buffer in one place.

Where the Lab fits

Production Planning in the Statadventure Lab, at $99 a month on its own or as an add-on, works out what to produce over the next 7, 30, 90, 180 and 365 days from the larger of forecast and customer orders, less stock. It compares the hours that takes with the hours each work center has and lists the production orders to add. Its Capacity planning page shows load by week and the bottleneck, and the Production schedule page turns released orders into a finite schedule. See production planning software.

Want to see demand set against work center hours?

The live demo runs a sample pumps and valves plant: what to produce, load by week and a finite schedule. No sign-up.

Frequently asked questions

What is the difference between the MPS and MRP?

The MPS says how many end items to finish in each week. MRP takes the MPS and explodes it through the bills of materials to plan the components and materials, offset by their lead times.

What is the difference between the MPS and the production plan?

The production plan, often agreed in sales and operations planning, sets monthly rates by product family. The MPS breaks that plan into end items and weeks, and it is what MRP and the shop schedule work from.

How far ahead should the MPS go?

At least as far as your cumulative lead time, the longest chain of purchasing and production time for the item. Going further gives purchasing and capacity decisions more warning.

Why does available to promise use customer orders and not the forecast?

ATP answers how much of the planned supply is not yet promised to a customer. The forecast is what you expect to sell; ATP is the stock and planned production still free to sell against it.